WE Report

Lessons Learned

Lesson Learned





By: Giacomo Bonomo

Report No.

6369

Discipline/Origin

Drilling
Own Experience

Well

Toppand East
35/11-5, 39/11-29S

Date created

2024/06/06
549 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Other
Other

COSLPromoter

What happened in Surface section:
Not possible to reach the profile depth with the ROV jetting tool, as the RMR external adapter top is about 2,3m above the profile and the ROV arm length is 1,5 m.

What Was Planned

RMR with external adapter is used for the operations. The adapter is kept installed while running casing and HPH in order to be able to get mud return and avoid dumping of KCL mud. Before running the HPH it is recommended to clean the profile in the LPH. Clay/gumbo may prevent correct landing of the HPH in the LPH.

What Was Learned

Additional run with jetting tool required to clean the wellhead profile.

What Actions Are Required

Ensure in future wells that a jetting tool is available onboard when RMR external adapter is used.